The completion of the Project Request/Authorization
Form is required for each project over $1,000. (See
forms) It is used for all planning, remodeling,
new construction, and major repairs and/or replacements.
The form is not used for State capital construction
or controlled maintenance.
All applicable information requested on the form must
be provided. The approval process must be completed
in the order shown below. Approval signatures
are required based on the dollar estimates of, or increases
for, the project.
- The requester prepares and signs the form.
The source of funding, including the account
number, is entered, if known. The individual must
have signature authority on the account or obtain
an authorized signature.
- The Auxiliary Services Assistant Vice President
signs for all projects of $1,000 or more if auxiliary
dollars are used to fund the project.
- The Director of Facility Services reviews
and signs the form for projects of $5,000 or
more.
- The General Accounting Office assigns the
account name and number. If the General Accounting
staff are unsure what the source of funding is, they
contact Facility Services to determine the proper
coding. General Accounting personnel initial and date
the account number portion of the form, or, if all
required signatures are on the form at this point,
move directly to #8.
- The area vice president of the project
approves the actual project and funding if costs are
projected to be $25,000 or more.
- The Director of Budgets reviews and approves
the project for funding if the costs are to be $25,000
or more.
- The Senior Vice President for Administrative
Services approves the project if $50,000 or more is
to be spent and obtains the approval of the
Board of Trustees if the project exceeds $300,000.
- At any point, when all required signatures
are obtained on the form, it is returned to the General
Accounting Office. At this time, the fund accountant
and Director of General Accounting sign the form.
In addition, a project number is assigned and
a copy is made for each individual that has signed
the form. If Facility Services is to complete the
project, the Facility Services Work Control
Center assigns their Project Job Order Number
and enters it on their copy.
If it is necessary for a project to be revised, a copy
is made of the first completed project form. The
changed information is entered in the "Revised
Budget" column along with the work "revision"
and the date written in the upper right hand corner.
Each of the signers of the original form must initial
and date the revised form before the project revision
is authorized.
|